How to Design a Commercial Roaster Exhaust System for Giesen W6A

The Giesen W6A requires 520 CFM minimum exhaust at the stack connection per Giesen factory spec (document GEX-W6A-2024).

Exhaust design must account for afterburner add-on (+15% CFM), make-up air, and local AHJ separation distances from air intakes. This guide sizes ducting, fan static pressure, and make-up air for a typical 6 kg production roastery bay.

Decision box

Choose your approach before starting
OptionWhen to useNotes
Roof stack directSingle-storey bayLowest static loss
Horizontal run to wall fanMulti-tenant buildingCheck lease restrictions
Afterburner inlineStrict emission limits+15% CFM, +$18k USD

Procedure

  1. Step 1: Confirm CFM requirement

    Base W6A: 520 CFM. Giesen afterburner option: add 78 CFM (15%). Size fan at 110% of total for filter loading degradation over 6 months.

  2. Step 2: Calculate duct diameter

    At 600 CFM and 10 m/s velocity, minimum round duct ID = 180 mm (7"). Rectangular equivalent: 200 × 150 mm. Reduce elbows — each 90° adds 0.3" static loss equivalent to 3 m straight run.

  3. Step 3: Select fan and motor

    Target 1.2" WC static at fan inlet. Typical selection: backward-inclined centrifugal, 0.75 kW motor, VFD for balance. Avoid axial fans in chaff service — clogs blade pitch.

  4. Step 4: Design make-up air

    Provide 510 CFM make-up (85% of 600) via dedicated louvre or HVAC interlock. Negative pressure > 5 Pa in roast room pulls café odours into drum — unacceptable for QC.

  5. Step 5: AHJ submission and install

    Submit Giesen exhaust diagram, fan curve, and separation distances. Typical US requirement: 3 m from air intakes, 1 m above parapet. Schedule pre-inspection before insulation wrap.

FAQ

Can W6A share exhaust with café HVAC?
No — dedicated roast exhaust required. Chaff and VOC load contaminates general HVAC.
What filter before fan?
Giesen cyclone separator standard; add baghouse only if local code requires PM limits below 50 mg/m³.
EU vs US stack codes?
EU references EN 13792 for coffee roasting emissions; US uses local BACT. Netherlands often requires afterburner in urban zones.
How often to clean duct?
Inspect quarterly; full chaff clean every 500 roast hours or 6 months, whichever first. NFPA 664 applies to combustible dust.